Tag Archives: Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail

Citizens and Legislators Decry Poor Oversight of California High-Speed Rail

California State Assembly Speaker Toni Atkins claimed in a November 3, 2015 letter that the Assembly would be “undertaking a broader range of oversight activities in 2016” related to California High-Speed Rail. She wrote that “oversight mechanisms have already been put in place” and “that oversight will continue in January through the Assembly Budget Subcommittee on Resources and Transportation.”

California Speaker Atkins High-Speed Rail Oversight PromiseThat promised committee oversight hearing about California High-Speed Rail referenced by Speaker Atkins happened on January 27, 2016. (See agenda and staff report here.) Representatives of Citizens for California High-Speed Rail Accountability (CCHSRA) were at this hearing of the California State Assembly Budget Subcommittee No. 3 on Resources and Transportation. (See the list of committee members here.)

As expected, the alleged “oversight” of the validity of the California High-Speed Rail Authority’s estimates of project costs and schedule was inadequate and deceptive. Citizens and state legislators concerned about the project were given minimal opportunity to challenge the “high levels of confidence” that California High-Speed Rail Authority officials claimed to have about the project.

No one from Citizens for California High-Speed Rail Accountability (CCHSRA) or any other organization critical of the project was invited to be a panelist, of course. Invited panelists were Dan Richard, Chairman of the California High-Speed Rail Authority Board of Directors, Jeff Morales, Chief Executive Officer of the California High-Speed Rail Authority, and Louis Thompson, Chairman of the California High-Speed Rail Peer Review Group.

Similar to past oversight committee meetings, the chairperson of the committee (Assemblyman Richard Bloom) limited the time of the hearing to 90 minutes and the allotted time given to public comment to one minute. Assemblyman Jay Obernolte (R-Hesperia) asked questions. After questioning various claims about the project and receiving empty answers, Assemblyman Jim Patterson (R-Fresno) futilely requested the committee chairman to allow additional time for discussion of the most expensive construction project in human history.

A chief focus of the hearing was rebutting an October 24, 2015 Los Angeles Times article ($68-Billion California Bullet Train Project Likely to Overshoot Budget and Deadline Targets). It was also emphasized that the California High-Speed Rail Authority would soon issue a new 2016 Business Plan that would essentially make the past irrelevant.

Brief public comment critical of project oversight came from Assemblywoman Patty Lopez (D-San Fernando), representatives of two train rider organizations, a representative of several communities in Los Angeles County affected by the proposed route, and five residents of the San Joaquin Valley, including multiple representatives of Citizens for California High-Speed Rail Accountability. Valley resident Shauna Green simply declared that based on her past experience with the California High-Speed Rail Authority and the testimony at the hearing, people should know that “they’re liars.”

A few professional lobbyists defended the California High-Speed Rail Authority during public comment. Prominent among them was a representative of the California Labor Federation and a representative of the State Building and Construction Trades Council of California, who praised the agency’s transparency and eagerness for oversight.

Video of the Hearing (courtesy of Derail HSR)

Assembly Budget Committee High Speed Rail Oversight Committee – January 27, 2016 – Authority Chairman Dan Richards and Assemblyman Das Williams comments

Assembly Budget Committee High Speed Rail Oversight Committee – January 27, 2016 – Assemblyman Jay Obernolte Questions

Assembly Budget Committee High Speed Rail Oversight Committee – January 27, 2016 – Assemblyman Jim Patterson Questions

Assembly Budget Committee High Speed Rail Oversight Committee – January 27, 2016 – Assemblywoman Patty Lopez Comments and Public Comments

Papers Submitted to Committee

Population Growth and the Need for High-Speed Rail – Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail

4,300 Miles of Highway Lanes as an Alternative to High-Speed Rail – Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail

The Green Train – Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail

The Truth About Public and Private Financing for the California HSR System – Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail

Letters Regarding California High-Speed Rail Oversight

Assembly Speaker Must Strengthen High-Speed Rail Oversight – Background from Citizens for California High-Speed Rail Accountability (CCHSRA) – November 11, 2015

Request to Assembly Speaker Toni Atkins for Legislative Subpoenas to Obtain Internal California High-Speed Rail Authority Documents – Assembly Minority Leader Kristen Olsen – October 28, 2015

Denial of Request for Legislative Subpoenas to Obtain Internal California High-Speed Rail Authority Documents – Assembly Speaker Toni Atkins – November 3, 2015

Letter to Assembly Speaker Toni Atkins Regarding Inadequate Legislative Oversight of California High-Speed Rail – Citizens for California High-Speed Rail Accountability (CCHSRA) – November 10, 2015

News Coverage

Bullet Train Chairman Projects Lower Cost, Longer Timeline – Associated Press (in San Francisco Chronicle) – January 27, 2016

Bullet Train May Take Longer to Build But Cost Less Than Originally Estimated, Official Says Los Angeles Times – January 28, 2016

High-Speed Rail Officials Seek to Reassure Lawmakers – KQED – January 27, 2016

Lawmakers Demand Answers from High-Speed Rail Leaders – KCRA (Channel 3) Sacramento – ‎January 27, 2016‎

High-Speed Rail Opponents Allege Conflict of Interest, Lack of OversightSan Fernando Sun – January 28, 2016

High Speed Rail Hides from Oversight – commentary by Morris Brown – Fox & Hounds – February 1, 2016

Press Releases

Assemblyman Patterson Questions Rail Officials on Major Shift in Project Plans – California State Assemblyman Jim Patterson – February 2, 2016

Vidak Calls Assembly Hearing on High-Speed Rail “Another Pitiful Whitewash” – California State Senator Andy Vidak – January 27, 2016

Rebutting Claims About California High-Speed Rail as a Highway and Airport Alternative

Below is a summary (abstract) of a report submitted to the California High-Speed Rail Authority board by Mark R. Powell of Against California High Speed Rail at the board’s November 9, 2015 meeting.


Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail

24,300 Miles of Highway Lanes as an Alternative to High-Speed Rail
by Mark R. Powell
October 30, 2015

The Authority’s most recent hyping of the need for high-speed rail, a June 2015 brochure entitled California High-Speed Rail Big Picture (2015), makes the claim that Phase 1 Blended, connecting San Francisco and Los Angeles, provides a transportation capacity equivalent to 4,300 new highway lane miles, 115 additional airport gates, and four new airport runways costing $158 billion. A second claim is that high-speed rail provides this capacity at half the cost.

This paper dissects these deceptive claims where the Authority uses “capacity” instead of “ridership” knowing full well that the theoretical capacity of Phase 1 Blended will dwarf its ridership and that the itemized highway lane miles will not be necessary this century, if ever, whether Phase 1 Blended is built or not built.

The paper then traces the evolution over two decades of the asserted highway benefits of high-speed rail, from the thousands of miles of highway lanes reported in the Authority’s 2005 California High-Speed Train Final Program EIR/EISback to earlier minimal assertions made in its first business plan and those made by its predecessor, the Intercity High-Speed Rail Commission.

Lastly, this paper looks at California Department of Transportation (Caltrans) traffic data and Caltrans long range planning documents. The data and planning documents prove how the Authority grossly overestimated future highway infrastructure needs for the year 2016 in its 2005 California High-Speed Train Final Program EIR/EIS and attempts to give readers information sufficient to see for themselves high-speed rail’s true impact on future highway needs over the next 20 years.

Read the full report at the California High-Speed Rail Authority website at Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail or at the Citizens for California High-Speed Rail Accountability website at Pushing Back on the California High-Speed Rail Authority’s Myths About High-Speed Rail.

###